SHIFT Simulator — Input/Output Interface

Markdown report of a non-markdown source document.

Source docs/_originals/Simulator Interface Input-Output sheet.pdf
Format PDF, 10 pages, 556 kB
MD5 0712f05593c39897abc8f651834bebde
Owner AI & Control Systems cluster
Document status Draft v0.1 — living document, TBD items unresolved
Report generated 2026-07-25

Note

Tables in the source PDF are rendered in a layout that machine extraction scrambles (symbol, name, unit and note columns interleave). The tables below are reconstructed — the content is the source's, the column alignment is this report's. Where a mapping was ambiguous it is flagged inline. Check against the original PDF before relying on any single row for implementation.

Purpose

Defines the contract between the SHIFT microgrid simulator and everything that talks to it:

  • the AI/RL policy,
  • the rule-based baseline,
  • the validation/benchmark layer,
  • the Economics team's downstream cost and CO₂ accounting.

It covers what the simulator consumes (configuration, exogenous time-series, control actions) and what it returns at every timestep.

"It is a living document — items flagged TBD need a decision from the cluster or whoever."

This document is the direct descendant of Shift Input Data — §1 explicitly refers to "the constants Robert's doc lists in bold."


0. Conventions

Timestep

Symbol: dt

Default assumption 1 hour — matches typical PV/load profiles and the one-year benchmarking horizon in the project brief. Whether a sub-hourly step is needed for battery fast-response behaviour is TBD.

"I did 1 hour for this cause 15 mins time steps will be quite compute heavy for RL training, so we do need to talk about that."

Sign conventions

Quantity Positive means Negative means
P_battery discharging (supplying the bus) charging (absorbing from the bus)
P_grid importing from grid exporting to grid
n_H2_net net production into tank net consumption from tank

All other power values — P_PV, P_electrolyser, P_fuelcell, P_load — are non-negative by definition.

Power balance

The invariant the simulator must satisfy at every step:

P_PV_used + P_fuelcell + P_grid + P_battery
      = P_load_served_critical + P_load_served_noncritical + P_electrolyser

Any residual after the policy's action is absorbed by unmet load — with critical load prioritised (see §4).

Units

SI throughout: power in W, energy in Wh, mass in kg, amount in mol, time in s (or h for hourly steps). TBD to lock down before code is written.

"I don't know the conventions for this, I let AI handle this, not an electrical engineer sorry."


1. Static configuration inputs

Set once per simulation run.

1.1 Electrolyser

Symbol Name Unit Notes
N_c_ele Number of cells Usually difficult to find
mu_F Faraday efficiency Fall back to literature average (~0.950.99 for PEM)
P_Electro_max Rated / max power W
P_ele_min Minimum operating power W Below this the electrolyser shuts off (efficiency cliff)
I_ele_min Minimum operating current A Alternative to P_ele_min
cal_H2 H₂ production calibration factor If we end up reading H₂ flow from measured data

1.2 Fuel cell

Symbol Name Unit Notes
N_c_fc Number of cells
utilisation_fc H₂ utilisation %
P_FuelCell_max Maximum output power W Project spec: 100 kW
V_fc_min, V_fc_max Operating voltage range V

1.3 Hydrogen tank

Symbol Name Unit Notes
E_H2_max Maximum electrical energy capacity of the storage tank J
V_H2_max Maximum stored volume L (or kg) Project spec: up to 200 kg total across two tanks
V_H2_init Initial fill level L (or kg)
T_tank Operating temperature K TBD — isothermal assumption likely fine
p_tank Operating pressure atm (or bar) TBD — isobaric vs. ideal-gas model

1.4 PV

Symbol Name Unit Notes
A_PV Total panel area Project spec: 2,300 m²
mu_PV Panel efficiency
P_PV_max Inverter / rated cap W Optional; if set, clipping occurs above this

1.5 Battery

Symbol Name Unit Notes
E_rated Rated energy capacity Wh
E_battery_max Maximum energy capacity Wh
Q_rated Rated charge capacity Ah
P_battery_max Max (dis)charge power (assuming both are identical - this is the current assumption in the Simulink Controller) W
P_battery_charge_max Max charge power W
P_battery_discharge_max Max discharge power W
SoC_init Initial state of charge — (01)
SoC_min, SoC_max Operating window — (01) E.g. 0.10.9
eta_batt_ch, eta_batt_dis Round-trip efficiencies Often split into charge & discharge

1.6 Load

Symbol Name Unit Notes
V_load Bus voltage V Constant, per Robert's note

1.7 Grid

Symbol Name Unit Notes
P_grid_max Max connection capacity (import & export) W Constant, per Robert's note
V_grid Bus voltage V

2. Per-timestep inputs

2.1 Exogenous time-series

Read from data; not under policy control.

Symbol Name Unit Source / note
G(t) PV generated power W Forecasted
L_crit(t) Critical hospital load demand W ICU, life-support, etc. — must always be served
L_noncrit(t) Non-critical hospital load demand W Lighting, HVAC, admin
grid_on(t) Grid availability (1/0) Models outages
price(t) Grid electricity price €/kWh Import & export prices — TBD whether they differ
CO2_int(t) Grid carbon intensity kg CO₂/kWh For emissions accounting

2.2 Control inputs

From the AI/RL policy or the rule-based baseline. At each timestep the controller emits setpoints, not direct power flows — the simulator clips them to physical limits and reports actuals.

Symbol Name Unit Range
u_ele(t) Electrolyser power setpoint W [0, P_ele_max]; values in (0, P_ele_min) round to 0 (off)
u_fc(t) Fuel cell power setpoint W [0, P_fc_max]
u_batt(t) Battery setpoint (signed) W [-P_batt_charge_max, P_batt_discharge_max]
sw_ele(t) Electrolyser ON/OFF 1/0 Optional — can be folded into u_ele = 0
sw_fc(t) Fuel cell ON/OFF 1/0 Optional — can be folded into u_fc = 0

On the grid: the grid is treated as the slack bus — whatever the power-balance residual is after all other components act, the grid absorbs, within P_grid_max and grid_on(t). The RL action space therefore probably does not include the grid directly.


3. Per-timestep outputs

3.1 State variables

Carried forward to the next step.

Symbol Name Unit
SoC(t) Battery state of charge — (01)
E_battery_SOC(t) Energy currently present in battery J
E_H2_SOC(t) Electrical Energy that can be currently extracted from the Hydrogen Storage Tank J
H2_level(t) H₂ stored in tank mol (or kg)
T_tank(t) Tank temperature K (only if non-isothermal model)
p_tank(t) Tank pressure bar (if modelled)

3.2 Power flows

Symbol Name Unit
P_PV(t) PV power available given irradiance W
P_PV_used(t) PV power actually consumed W
P_PV_curtailed(t) PV potential that was thrown away W
P_ele(t) Actual electrolyser consumption W
P_fc(t) Actual fuel cell output W
P_batt(t) Actual battery flow (signed) W
P_grid(t) Actual grid flow (signed) W
P_load_served_crit(t) Critical load served W
P_load_served_noncrit(t) Non-critical load served W
P_load_P(t) Power to be covered after PV (+ve = remaining power shortage, -ve = surplus to be used) W
P_load_PB(t) Power to be covered after PV and Battery (same convention as P_load_P) W
P_load_PBH(t) Power to be covered after PV, Battery and Hydrogen stroage tank (same convention as P_load_P(B)) W
P_battery_cont(t) Power amount the controller determines the battery should (dis)charge at (accounting for battery properties and demand) W
P_FuelCell_cont(t) Power amount the controller determines the fuel cell should provide (accounting for it's properties and demand) W
P_Electro_cont(t) Power amount the controller determines the electrolyser should extract (accounting for it's properties and demand) W

3.3 Mass flows (hydrogen)

Symbol Name Unit
n_H2_prod(t) H₂ produced by electrolyser mol/s (or kg/h)
n_H2_cons(t) H₂ consumed by fuel cell mol/s (or kg/h)
n_H2_net(t) Net flow into tank mol/s

3.4 KPIs and accounting

"the heart of the task"

Symbol Name Unit Notes
unmet_crit(t) Unserved critical load W Must be near-zero — primary resilience KPI
unmet_noncrit(t) Unserved non-critical load W Restated as a KPI for clarity
curtailment(t) = P_PV_curtailed(t) W
cost(t) Operating cost of this step TBD — see §5
CO2(t) Emissions of this step kg CO₂ TBD — see §5

3.5 Diagnostic / efficiency outputs

Recommended. Ties directly to AI Efficiency Improvements, which flagged ~3040% electrolyser losses and ~40% fuel-cell losses as the biggest optimisation targets. If the simulator returns per-step efficiencies, the RL reward and the post-hoc analysis can both attack those losses directly.

Symbol Name Unit
eta_ele(t) Electrolyser efficiency this step
eta_fc(t) Fuel cell efficiency this step
eta_PV(t) Effective PV efficiency this step
eta_batt(t) Battery round-trip-equivalent

4. Priority rules the simulator enforces

Not I/O, but contract-level — the policy needs to know what the simulator will do with a setpoint that violates physics or safety.

  1. Critical load is sacred. If the policy's setpoints leave critical load unserved while the battery has charge, the fuel cell can run, or the grid is available, the simulator overrides the policy in that order and reports the override (e.g. via an output flag) so it shows up in training.
  2. State limits are hard. SoC ∈ [SoC_min, SoC_max], H2_level ∈ [0, V_H2_max]. Setpoints that would breach these are clipped; the difference shows up as P_batt(t) vs u_batt(t).
  3. Electrolyser dead-zone. Setpoints in (0, P_ele_min) are rounded to 0.
  4. Grid outage. If grid_on(t) = 0 then P_grid(t) = 0 regardless of slack residual; the residual becomes unmet_* or curtailment.

5. Open questions

Need answers before v1.0.

  • Cost & CO₂ scope. Flagged TBD in §3.4. If Economics handles these downstream, the simulator only needs to return P_grid(t) plus exogenous price(t) and CO2_int(t), and Economics computes cost/CO₂ themselves. If the simulator computes them, it also needs to know whether there is an O&M cost per kWh through the electrolyser/fuel cell, a degradation cost, and so on.
  • Tank model. Isothermal + ideal gas, or do we need temperature and pressure dynamics?
  • Battery degradation. Modelled or ignored?
  • Sub-hourly dynamics. Does the battery's fast-response role require dt < 1 h? If so, mixed time-scale handling between battery (minutes) and electrolyser (hours) becomes a design question.
  • Action space format. Continuous setpoints (u_ele ∈ [0, P_ele_max]) vs. discrete buckets — affects what the RL team expects as input.
  • Forecast vs. realised exogenous inputs. The policy may see a forecast of G(t+1) and L(t+1); the simulator advances with the realised values. Decide whether the simulator delivers both or only realised.
  • Critical vs non-critical split — data availability. Confirm with the hospital data source whether the load profile can actually be split, or whether we need a proxy fraction (e.g. assume X% of total load is critical).
  • Mutual exclusion of electrolyser and fuel cell. Should the action space structurally prevent simultaneous operation (mode-switch / hybrid action space), or allow them independently and let the reward penalise simultaneous operation? Has efficiency, sample-efficiency, and policy-expressiveness trade-offs.

Cross-document notes

Three consistency issues between this document and its neighbours:

Issue Detail
Naming convention This document uses physics-style symbols (P_PV, SoC(t), u_ele). RL State Variables and RL Action Variables use descriptive identifiers (PV_Generation, Battery_SOC, Electrolyzer_PowerSetpoint). Neither references the other; one must win.
State coverage This sheet omits component temperatures, stack health, and water level, which the RL state doc lists. Consistent with the isothermal/no-degradation assumptions flagged TBD above.
Action coverage This sheet accepts 5 control signals; the RL action doc lists 16. Grid import/export and load shedding are deliberately excluded here (slack bus, and outcome-not-action respectively); PV curtailment control, thermal management, and mode supervision are genuine gaps.

Load-tier terminology also differs from Energy Management's BIDMC/UCSD Energy Flow and Balances, which uses a three-tier model (Tier 1 critical / Tier 2 essential / Tier 3 non-critical) against this document's two-way split (L_crit / L_noncrit).